1. Giving
training : Persona is given training regulations and practices about HACCP system . 2. Pre-preparing of establishing of HACCP
system : The following works are realized in this phase :
- Production process is researched, flow diagram is prepared
- HACCP team leader is determined
- Detailed Project works and time plans are prepared
3. Occurring of HACCP team: Team is occurred that in different disciplines people established HACCP system in the shortest time
and the most efficiency.
4. Pre-sufficiency program : Hygiene practices have to apply in high standards in company to apply HACCP system. Therefore needed
works will be directed.
5. Product definitions : Using shapes and final product identifications are documented to determine hazards better.
6. Process flow diagrams: For every product/product group, process flows are determined.
7. Hazard and risk analysis : In process flow for every level hazards are determined according to possibility of occurring and
given harmful.
8. Determining of critical control points: Critical control points are determined according to hazard analysis.
9. Identification of limits in critical phases : Limits and objective worth's are determined for every critical control points.
10. Monitoring system : Control system is established to control critical control points with described test and observation.
11. Corrective prevention : If there is devotion in critical control points, to be done operations are documented determining.
12. Verification : To test sufficiency and suitable to standard of HACCP system , methods are determined and documented.
13. Product identifications : Record system is developed to provide monitoring with evidence in audit.
14. Taking of corrective and preventive actions: Internal audit is planed to monitor practices after establishing of system
and corrective and preventive actions are prepared and practiced according to results of internal audit.
15. Application of certification :
|